Several roadways and alleys within the City have been earmarked for repairs as part of the City’s 2019 Street Repair and Maintenance Program. A list of these roadways and alleys, as well as the type of work being performed is included below. Please note that the City will be providing updates regarding these projects such as parking restrictions, road closures, water interruptions, etc. as they occur.

Friday
Aug162019

Charles (Between Chelsea and Roosevelt)

Project Description: Furnishing new curbs to the street, and milling and overlaying the street surface.

Project Status: Curb work is currently underway. Expected completion for curb work is August 30. Milling and overlay is anticipated to be completed by the end of September. 

Friday
Aug162019

Dawson

Project Description: Curb repair, drainage improvements, and milling & paving the street surface.

Project Status: Spot curb repair has been completed. Milling and overlay is anticipated to be completed by the end of September. 

Friday
Aug162019

Ferndale/Mayfield Header Alley and Mayfield in-fill

Project Description: Curb repair, drainage improvements, and milling & paving the street surface.  Spot in-fill of pavement in areas with settling.

Project Status: Spot curb repair has been completed. Milling and overlay and in-fill is anticipated to be completed by the end of September. 

Friday
Aug162019

N. Remington (Between Denver and Maryland)

Project Description: Curb repair, drainage improvements, and milling & paving the street surface.

Project Status: Spot curb repair has been completed. Milling and overlay is anticipated to be completed by the end of September. 

Friday
Aug162019

Powell (Between Drexel and Columbia)

Project Description: Curb repair, drainage improvements, and milling & paving the street surface.

Project Status: Spot curb repair has been completed. Milling and overlay is anticipated to be completed by the end of September.